Narrative description of the Project:

The Second Ho Chi Minh City Environmental Sanitation Project (HCMCES-2, a total project budget of 500 mil. USD), which aims at treating wastewater intercepted for the NLTN basin and from three urbanized areas in District 2. Main components of the project are:

Component 1: Interceptor – a large diameter pipe (about 3.2 meters in diameter; length of about 8 kilometers) that will convey the wastewater that is currently being discharged on the east side of the Saigon River without treatment to the wastewater treatment plant in District 2;

Component 2: Wastewater Treatment Plant, treating the wastewater collected in the NLTN basin and in the D2 areas. The plant is being designed for a capacity of 480,000 m3/day;

Component 3: Sewerage in District 2 Area – an additional! sewers and interceptors will be installed in three areas of District 2, with wastewater thus collected to be transferred to the Interceptor or directly to the WWTP;

Scope of Work: Preparation of specialized urban master plan for storm drainage and sewage system covering in Ho Chi Minh city’s entire areas, from present to 2030 and 2050 based on the updated master plan in Ho Chi Minh city

The Consultant provided a full service of the topographical, hydrological, water quality sampling and analysis and measurement of cross-sections of the rivers/canals network system above and under the water, survey of the 17,500 manholes and 927 km sewer system as well as provided technical inputs for HCMC master planning for storm drainage and sewage system